Plans to offer grid ‘amnesty’ for up to 8GW of projects

Simon Osuji by Simon Osuji
August 16, 2023
in Energy
0
Plans to offer grid ‘amnesty’ for up to 8GW of projects
0
SHARES
0
VIEWS
Share on FacebookShare on Twitter


Ofgem and National Grid have set out plans to free up to 8GW of grid connection capacity from slow-moving developers, without incurring penalties.

Both groups published letters on Tuesday in response to a proposed Transmission Entry Capacity (TEC) Amnesty, which would allow contracted projects who have applied to the scheme to terminate or reduce their agreement without the usual fees.

NGESO confirmed around 50 projects have applied, with the cohort expected to remove or delay up to 8GW of generation from the queue, freeing up space for other schemes to progress.

“This therefore represents a clear opportunity to release capacity which is no longer required sooner than it otherwise would be, helping to improve connection timescales for customers,” Ofgem noted in its response.

The regulator said removing these projects would offer “clarity” on connections and works that can be stopped and would allow NGESO to provide other customers with “more timely” connection offers.

It pointed to the “significant” existing queue, in which over 340GW of new generation plants hold connection agreements.

Moreover, over 40% of all new generation capacity holding transmission connection agreements today have connection dates of 2030 or beyond – some as late as 2037.

NGESO asked for confirmation from Ofgem of its approach of not applying a Cancellation Charge, which deviates from the current framework set out in the Connection and Use of System Code (CUSC).

It also asked for protection for consumers who could face greater costs owing to the lack of recovered of cancellation charges.

Transmission operators would also be required to provide justification for each project terminated of any spend greater than £1m.

The process is expected to be time-limited until 30th September 2024 to grant NGESO sufficient time to facilitate the processing.

It comes a wider offensive by ESO and the regulator to tackle slow grid connections in a bid to ensure the system can meet ambitious decarbonisation targets.

Recommended for you

EGL2 hitachi

Eastern Green Link 2: Hitachi wins work on major Scotland-England grid link



Source link

Related posts

Why Dangote keeps buying U.S. crude despite Africa’s 120 billion barrels of proven reserves

Why Dangote keeps buying U.S. crude despite Africa’s 120 billion barrels of proven reserves

June 9, 2025
ReconAfrica plans fresh drilling in Namibia with $7.3million share sale

ReconAfrica plans fresh drilling in Namibia with $7.3million share sale

June 9, 2025
Previous Post

Study uses genomic data to produce high-resolution serial interval estimates for COVID-19

Next Post

Rand inches up before retail sales data

Next Post
Rand inches up before retail sales data

Rand inches up before retail sales data

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

RECOMMENDED NEWS

Aamal Company Q.P.S.C. (“Aamal”) Financial Results for the year ended 31 December 2024

Aamal Company Q.P.S.C. (“Aamal”) Financial Results for the year ended 31 December 2024

3 months ago
OpenAI, Meta, and Orange collaborates to train AI models on African languages

OpenAI, Meta, and Orange collaborates to train AI models on African languages

7 months ago
Delays push Army’s hypersonic missile to fiscal 2025

Delays push Army’s hypersonic missile to fiscal 2025

12 months ago
NiMet forecasts three-day sunshine, cloudiness starting on Sunday – EnviroNews

NiMet forecasts three-day sunshine, cloudiness starting on Sunday – EnviroNews

3 weeks ago

POPULAR NEWS

  • Ghana to build three oil refineries, five petrochemical plants in energy sector overhaul

    Ghana to build three oil refineries, five petrochemical plants in energy sector overhaul

    0 shares
    Share 0 Tweet 0
  • When Will SHIB Reach $1? Here’s What ChatGPT Says

    0 shares
    Share 0 Tweet 0
  • Matthew Slater, son of Jackson State great, happy to see HBCUs back at the forefront

    0 shares
    Share 0 Tweet 0
  • Dolly Varden Focuses on Adding Ounces the Remainder of 2023

    0 shares
    Share 0 Tweet 0
  • US Dollar Might Fall To 96-97 Range in March 2024

    0 shares
    Share 0 Tweet 0
  • Privacy Policy
  • Contact

© 2023 LBNN - All rights reserved.

No Result
View All Result
  • Home
  • Business
  • Politics
  • Markets
  • Crypto
  • Economics
    • Manufacturing
    • Real Estate
    • Infrastructure
  • Finance
  • Energy
  • Creator Economy
  • Wealth Management
  • Taxes
  • Telecoms
  • Military & Defense
  • Careers
  • Technology
  • Artificial Intelligence
  • Investigative journalism
  • Art & Culture
  • Documentaries
  • Quizzes
    • Enneagram quiz
  • Newsletters
    • LBNN Newsletter
    • Divergent Capitalist

© 2023 LBNN - All rights reserved.