First substation in place at Moray West

Simon Osuji by Simon Osuji
December 19, 2023
in Energy
0
First substation in place at Moray West
0
SHARES
0
VIEWS
Share on FacebookShare on Twitter


Boskalis has installed the first offshore substation at the Moray West wind farm, while work to install monopiles continues.

Developer Ocean Winds confirmed on Tuesday that Boskalis’ Bokalift1 crane ship had successfully installed the first platform at the site, around 13 miles off the Highland coast.

Ocean Winds – a 50:50 joint venture between ENGIE and EDP Renewables – is building the 880MW, 60-turbine Moray West project in the outer Moray Firth, next to the existing 950MW Moray East scheme.

The developer said heavy lift operations at the Port of Nigg – where components are being marshalled – and on-site were completed “successfully and safely.”

An export cable which has already been laid will now be pulled into the substation as offshore commissioning starts.

© Supplied by Ocean Winds
Bokalift 1 installs the first Moray West substation.

Bokalift1 will then move to install the second substation, while its sister vessel Bokalift2 will continue to install monopiles on site, subject to favourable winter weather.

Meanwhile last month saw delivery of the first of 62 transition pieces to Nigg as part of a rolling programme of delivery and installation.

The project is aiming to be fully operational in 2025, with an operational life of over 25 years

The announcement comes just days after a ceremony at supplier Siemens Gamesa, to present the company with the first of its 108-metre-long turbine blades being produced for the project at the firm’s factory in Hull.

In total, 180 blades for the projects 60 turbines, will be manufactured in Hull, following the completion of a huge expansion to the factory which enables the facility to make larger blades. Ocean Winds reports these will be longest used in a UK offshore wind farm so far.

© Supplied by Ocean Winds
Siemens Gamesa welcomed Gareth Davies MP, Exchequer Secretary to the UK Treasury and the team from Ocean Winds, to present the first 108-metre-long wind turbine blades being made in Hull for the Moray West offshore wind farm.

Gareth Davies MP, Exchequer Secretary to the Treasury, joined staff from Ocean Winds and Siemens Gamesa to mark the occasion.

Adam Morrison, Ocean Winds UK Country Manager said: “This is a fantastic milestone in our close working with Siemens Gamesa on our journey to commission these huge next-generation wind turbines.

“With each blade slightly longer than an international football pitch the scale of the engineering is impressive. We now look forward to ensuring the same high quality and high safety standards are achieved across all the wind turbine components prior to marshalling and pre-assembly in the north of Scotland, ready for installation of this class leading technology in 2024.

“The Moray West project is delighted to support the new investment at the Hull facility by Siemens Gamesa.”

Recommended for you

First delivery of transition pieces to Port of Nigg

‘Milestone’ moment for Moray West wind farm



Source link

Related posts

African countries with petrol rate reduction amid decline in crude oil price

African countries with petrol rate reduction amid decline in crude oil price

May 13, 2025
African Energy Bank scouts for president as launching date draws near

African Energy Bank scouts for president as launching date draws near

May 13, 2025
Previous Post

Anti-ransomware startup Halcyon lands fresh $40M tranche

Next Post

Ethics, governance and data for good at the AI & Big Data Expo

Next Post
Ethics, governance and data for good at the AI & Big Data Expo

Ethics, governance and data for good at the AI & Big Data Expo

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

RECOMMENDED NEWS

Research team develops an AI model for effectively removing biases in a dataset

Research team develops an AI model for effectively removing biases in a dataset

2 years ago
Cape Town’s water recycling project should not be privatised

Cape Town’s water recycling project should not be privatised

4 weeks ago
Northern Lights CCS project completes CO2 storage facilities

Northern Lights CCS project completes CO2 storage facilities

8 months ago
Microbial cell factories as a source of eco-friendly food and cosmetic coloring

Microbial cell factories as a source of eco-friendly food and cosmetic coloring

2 years ago

POPULAR NEWS

  • Ghana to build three oil refineries, five petrochemical plants in energy sector overhaul

    Ghana to build three oil refineries, five petrochemical plants in energy sector overhaul

    0 shares
    Share 0 Tweet 0
  • When Will SHIB Reach $1? Here’s What ChatGPT Says

    0 shares
    Share 0 Tweet 0
  • Matthew Slater, son of Jackson State great, happy to see HBCUs back at the forefront

    0 shares
    Share 0 Tweet 0
  • Dolly Varden Focuses on Adding Ounces the Remainder of 2023

    0 shares
    Share 0 Tweet 0
  • US Dollar Might Fall To 96-97 Range in March 2024

    0 shares
    Share 0 Tweet 0
  • Privacy Policy
  • Contact

© 2023 LBNN - All rights reserved.

No Result
View All Result
  • Home
  • Business
  • Politics
  • Markets
  • Crypto
  • Economics
    • Manufacturing
    • Real Estate
    • Infrastructure
  • Finance
  • Energy
  • Creator Economy
  • Wealth Management
  • Taxes
  • Telecoms
  • Military & Defense
  • Careers
  • Technology
  • Artificial Intelligence
  • Investigative journalism
  • Art & Culture
  • Documentaries
  • Quizzes
    • Enneagram quiz
  • Newsletters
    • LBNN Newsletter
    • Divergent Capitalist

© 2023 LBNN - All rights reserved.